What projects are attached to a prefabricated building permit application?
Article 22 of Türkiye's Zoning Law requires the petition to be accompanied by the title deed, the architectural project, the structural project, the electrical and plumbing projects with their drawings and calculations, and a sketch with benchmarks or dimensions. Being prefabricated does not change this list. Architects and engineers prepare the projects; we supply the technical drawings of the building.
What review period does the law set for a building permit application?
Under Article 22 of Türkiye's Zoning Law, if the application and its attachments are complete, the permit is issued within thirty days at most of the application date. If anything is missing, the authority notifies the applicant in writing within fifteen days. These are the authority's review periods; preparing the projects takes time on top, and we do not promise a timetable.
How long after the permit is issued must construction start?
Under Article 29 of Türkiye's Zoning Law, the period for starting construction is two years from the permit date. If construction does not start in that period, or the building is not finished within five years together with the starting period, the permit is deemed void and a new permit must be obtained.
Can a construction-site container stay on as a changing room when the work is finished?
Not automatically. Under Article 63 of the Regulation on Zoning in Planned Areas, for a construction-site building to be used after construction is completed, a building permit and an occupancy permit must be issued for it; otherwise an occupancy permit cannot be issued for the main building until the site building is demolished.
Can electricity and water subscriptions be opened without an occupancy permit?
Article 31 of Türkiye's Zoning Law states that buildings without an occupancy permit are not provided with electricity, water and sewerage services until the permit is obtained. For a changing-room building or café with showers and a kitchen, this means the building cannot be operated.
For how many years is a temporary (muvakkat) building permit granted?
Under Article 61 of the Regulation on Zoning in Planned Areas, it is granted by decision of the authority's executive committee (encümen) for at most 10 years; the period starts on the day the decision is annotated on the title deed. The same article limits the total construction area to 250 m², the number of storeys to 2 and the building height to 7.50 metres.
Can a prefabricated building put up without a permit be brought under a permit later?
Under Article 32 of Türkiye's Zoning Law, after a building is sealed the owner may, within one month at most, obtain a permit and ask for the seal to be lifted. Obtaining a permit depends on the building complying with the zoning status of the plot. If the authority determines that the building cannot be brought under a permit, the one-month period is not waited for.
I lease the land; can I apply for the business licence for the café?
The application forms attached to the Regulation on Business Opening and Operating Licences list "Rent" and "Owner" together as options for ownership status, so tenancy is anticipated for this licence. However, the application asks for building occupancy permit information; the building's permit and occupancy permit must be completed first, and the building permit requires the plot owner's consent.
This page is based on the texts of Türkiye’s Zoning Law (Law No. 3194), the Regulation on Zoning in Planned Areas and the Regulation on Business Opening and Operating Licences, read on 2 October 2026; it is general information, not legal advice. It covers buildings in Türkiye only, and no statement is made about the rules of other countries. Application depends on the plot’s zoning status; written information should be obtained from the relevant municipality’s zoning directorate. Legislation may change.